Global delivery from Hanoi, Vietnam ISO 9001:2015   ISO 27001:2013 hello@agiletech.vn (+84) 989 324 830

Agile vs waterfall SDLC: choosing a delivery model

In short

Waterfall runs the life cycle once in sequence and commits to a specification before construction begins. Agile runs the same life cycle repeatedly in short increments and commits to a direction rather than a specification. Neither is better in general: waterfall wins when the requirements are genuinely fixed and the cost of changing your mind late is lower than the cost of deciding slowly, which is the normal case for regulated, contractual and hardware-bound work. Agile wins when you expect to learn something from real users that will change what you build, which is the normal case for a product. The decision is not about which method is more modern, it is about whether your requirements are knowable in advance, and the honest answer for most projects is that some are and some are not.

Every software project passes through the same activities. Somebody decides what to build, somebody designs it, somebody writes it, somebody checks it, it goes live, and then it is maintained for years. That sequence is the software development life cycle, and the interesting question is never whether those activities happen. It is how many times you run through them, and how much you commit to before you start.

Waterfall answers: once, and commit to everything up front. Agile answers: many times, and commit to a direction and the next two weeks. Nearly every argument you will read about the two is an argument about that single structural difference, dressed up as a debate about culture.

This article gives the real difference, names the seven life cycle models a buyer will encounter, explains what each one demands from the client rather than from the vendor, and ends with the part that actually causes disputes: how the model you choose has to match the contract you sign. If you want the phase-by-phase walkthrough of the life cycle itself, along with what a contract needs to specify, that lives in our guide to the development process. This page is about choosing between the models.

Key takeaways

  • The life cycle is not the model. Requirements, design, build, test, deploy and maintain happen in every project. Waterfall passes through them once, agile passes through them repeatedly, and the phases themselves never disappear.
  • Waterfall is not a mistake and agile is not a discipline. Sequential delivery is the right answer for fixed-scope, certification-bound and integration-heavy work, and it fails specifically when requirements turn out to be guesses.
  • The seven models worth knowing are waterfall, v-model, incremental, iterative, spiral, agile and continuous delivery. Most real programs are hybrids, and naming the hybrid honestly beats claiming a purity nobody practices.
  • Agile is a family, not a method. Scrum sets a cadence, kanban sets a flow limit, extreme programming sets engineering practices, and lean sets a waste lens. Adopting the ceremony without the engineering practices is the most common failed adoption.
  • Agile transfers work to you, and this is the part nobody puts in the proposal. It needs an available decision maker, roughly every other week, for the life of the project. If you cannot supply that, agile will not just underperform, it will produce a worse result than a specification would have.
  • Your delivery model has to match your contract. Fixed price with a fixed scope is coherent, and so is time and materials with a fixed cadence. Fixed price with an agile process is the combination that produces disputes, because it prices a specification while promising to change it.
  • The choice is per workstream, not per company. A regulated core on a v-model and a customer-facing app on two-week sprints, inside one program, is a normal and correct architecture rather than an inconsistency.

The real difference, in one sentence

Waterfall runs the life cycle once and treats the specification as the commitment. Agile runs the life cycle repeatedly and treats the working increment as the commitment. That is the whole structural difference, and everything else follows from it.

Notice what does not change. Requirements analysis does not disappear in agile, it moves from a document written once into a conversation held repeatedly. Testing does not disappear in waterfall, it concentrates into a phase near the end instead of running continuously. Design does not vanish from either. The phases are properties of building software, not of a methodology, and any vendor telling you that agile means no documentation or no design is describing their own carelessness rather than the method.

What does change is when you find out you were wrong. In a sequential project, the specification is agreed in month one and the first honest feedback arrives when someone uses the software, which may be month nine. If the specification was correct, that is efficient: you paid for no rework and no meetings. If the specification contained a wrong assumption, you have built eight months of software on top of it, and the correction is expensive precisely because so much depends on it.

In an incremental project, working software appears every two or three weeks, so a wrong assumption surfaces while very little is built on top of it. You pay for that continuously in coordination: reviews, replanning, decisions, and a client who has to stay engaged. The trade is not quality against speed. It is early information against low coordination cost, and which one is worth more depends entirely on how certain your requirements really are.

The two shapes, compared on what actually differs

Sequential (waterfall)Iterative (agile)
Passes through the life cycleOnce, in orderRepeatedly, in short increments
What is committed up frontThe specificationThe direction and the next increment
First working softwareLate, near the endWithin the first few weeks
When a wrong assumption surfacesAfter it has been built uponBefore much depends on it
Cost of changing your mindRises steeply with timeRoughly flat, by design
Cost of coordinationLow, front-loadedContinuous, for the whole project
What it demands from the clientA correct specification, onceAn available decision maker, always
Natural contract shapeFixed price for fixed scopeTime and materials, or capped increments

The rows people argue about are the last three. The rows that decide project outcomes are the first four, and none of them are cultural.

One pass against many: where each model puts its commitmentA two-model comparison over four life cycle stages. The waterfall lane passes through each stage once toward a single late release, committing to a full specification before any code. The agile lane repeats the same stages in short increments, committing only to a direction and the next increment, testing continuously and releasing repeatedly. Decide Design and build Verify Release Waterfall Full spec signedbefore any code One longconstruction pass Test phase nearthe end One release, late Agile Direction only,plus nextincrement Short increments,working each time Testing runscontinuously Release, then loopback
The same six activities in both rows. Sequential delivery spends its single pass building toward one release; iterative delivery reaches a release repeatedly and returns. Nothing here is a measurement, it is the structure both models are usually described in words alone.

The seven life cycle models worth knowing

Waterfall and agile are the two poles of a spectrum with useful positions in between. A buyer who knows all seven can read a proposal properly, because a vendor who says "we work in an agile way" has told you almost nothing, while a vendor who says "incremental delivery with a v-model verification gate before each release" has told you a great deal.

The models below are ordered from most sequential to most continuous. Each one exists because it solved a real failure of the one before it, which is why the list is worth reading as a history rather than as a menu.

The seven models, what each one fixed, and what it costs you

Sequential

Waterfall
One pass, each phase completed before the next begins. Fixes chaos: it makes cost, scope and date knowable up front. Costs you a specification that has to be right, and a late first look at working software.
V-model
Waterfall folded so every design phase is paired with the test phase that verifies it. Fixes untraceable testing: nothing is designed without a matching verification. Costs you heavy documentation, and it is the standard shape wherever an auditor will read your evidence.

Partially iterative

Incremental
The scope is split into slices, each delivered in a small sequential pass. Fixes the late first look while keeping a fixed overall scope. Costs you an architecture that can absorb slices in any order.
Iterative
The same product is refined repeatedly, each pass improving the whole rather than adding a new part. Fixes designs that cannot be got right on paper. Costs you rework, deliberately, because refinement is the mechanism.
Spiral
Repeated passes ordered by risk, each beginning with a prototype of the scariest unknown. Fixes betting a program on an unproven assumption. Costs you real risk analysis, which is a skill and a time budget.

Continuous

Agile
Short increments, working software each time, scope negotiated continuously against a fixed cadence and budget. Fixes the wrong specification. Costs you continuous client availability, which is the most commonly unpaid bill in software.
Continuous delivery
Agile plus the automation to release safely at any moment, so a release is a routine event rather than a project. Fixes the batch of finished work that sits unreleased for weeks. Costs you real investment in testing, pipelines and observability before it pays anything back.

Read the "costs you" column first. Every model buys a benefit by demanding something, and the demand is usually on the client rather than on the engineering team.

The seven models as a spectrum, from one pass to continuousFour tiers of life cycle model. Sequential holds waterfall and the v-model. Sliced holds incremental. Repeated holds iterative and spiral. Continuous holds agile and continuous delivery. Labels between the tiers state the failure each step was invented to address.SequentialOne pass Waterfall V-model Fixes: the first working software arrives far too lateSlicedFixed scope Incremental Fixes: some things cannot be designed correctly on paperRepeatedRefine orde-risk Iterative Spiral Fixes: the specification itself was a set of guessesContinuousAlwaysreleasable Agile Continuous delivery
Read top to bottom as increasing frequency of feedback and increasing coordination cost. The link labels between tiers name the specific failure each step was invented to fix.

Agile is a family, and the differences matter

Agile is a set of values, not a process, so nobody can literally do agile. What teams do is scrum, or kanban, or extreme programming, or some blend, and those are genuinely different in ways that show up in your calendar and your invoices.

The distinction that matters most to a buyer is between the frameworks that organize work and the practices that make changing software safe. Scrum and kanban organize. Extreme programming supplies the engineering discipline. A team running the ceremonies without the practices produces the most common failure in this whole field: a project that is very well coordinated while quietly becoming harder to change every sprint.

What each member of the family actually provides

CadenceFlow limitDefined rolesEngineering practices
ScrumYesNoYesNo
KanbanNoYesNoNo
Extreme programmingYesNoPartialYes
LeanNoPartialNoNo
Scaled frameworksYesNoYesNo

Read down the last two columns. Only extreme programming provides the engineering practices, which is why scrum is so often adopted alongside it rather than instead of it.

The vocabulary, in plain language

Sprint
A fixed period, usually one to three weeks, at the end of which something works. The length is fixed on purpose: when the deadline cannot move, scope becomes the thing that gets discussed, which is the entire mechanism.
Backlog
The ordered list of everything not yet built. Its order is the plan. An unordered backlog is a wish list, and a backlog nobody prunes becomes an archive of ideas the team has silently agreed to ignore.
Work in progress limit
The kanban rule that only so many items may be underway at once. Counterintuitive and effective: less started at the same time means more finished per week, because switching between unfinished things is where the hours go.
Definition of done
The written standard a piece of work must meet before anyone may call it finished. Without one, "done" quietly comes to mean "the code is written", and the testing and deployment debt accumulates invisibly.
Velocity
How much a team completes per sprint, useful only as that team's own forecasting input. It is not a productivity score and it does not compare across teams, because the units are locally invented.
Retrospective
The regular session where the team changes how it works. The one ceremony whose removal is unambiguously bad, because it is the only part of the process that improves the process.
Technical debt
Work deferred to go faster now, which charges interest in the form of every future change being slower. Real and sometimes worth taking on, dangerous when it is never named or repaid.

Terms a vendor will use in the first meeting. Knowing them is the difference between agreeing to a process and agreeing to a word.

Which is better: the honest answer

Neither, and the question is better replaced with a diagnosis. Ask instead: how certain are my requirements, and what does it cost me to be wrong late? Those two answers select the model, and they can be assessed before any methodology is chosen.

Requirements are genuinely fixed more often than agile advocates admit. A payroll engine implementing published tax rules, a device integration against a fixed protocol, a regulatory report with a mandated format: in all of these the specification is externally defined, discoverable up front, and not subject to user preference. Iterating to discover a requirement that is written down in a statute is not learning, it is a slower way of reading.

Requirements are guesses more often than sequential advocates admit. Anything whose success depends on whether people choose to use it, on how they behave when they do, or on a market that has not been tested is a hypothesis in a specification's clothing. Writing it in more detail does not make it more true, it only makes it more expensive to correct.

The most useful reframing is that this is a decision per workstream and not per organization. Most programs contain both kinds of work, and forcing one model across all of it means one half of the program is running under the wrong assumptions.

Selecting a model from the two questions that matter

Which model fits this workstream?

  • Requirements are externally defined and an auditor will read your evidence

    V-model, with verification paired to each design phase

    The specification is discoverable up front because somebody else wrote it, and the documentation the model demands is documentation you were required to produce anyway. Iterating here adds cost and no information.

  • Scope is genuinely fixed but you cannot wait months to see anything

    Incremental delivery inside a fixed overall scope

    You keep the up-front commitment on cost and scope while getting working software early. This is the model most misdescribed as agile in proposals, and it is often what the client actually wanted.

  • One assumption could invalidate the whole program

    Spiral, starting with a prototype of that assumption

    Ordering the work by risk rather than by architecture means the question that could kill the project is answered while canceling is still cheap.

  • Success depends on how real users behave

    Short increments with a real release each time

    The requirement does not exist yet in any knowable form. Only contact with users produces it, so the process has to be built around getting that contact early and repeatedly.

Work down the branches and stop at the first that describes your workstream. Most programs contain two or three of these at once, which is why the answer is per workstream rather than per company.

How this decision is made well, and how it is usually made

Do this

  • Decide per workstreamAssess certainty separately for the regulated core, the platform and the customer-facing app. They rarely share an answer.
  • Name the hybrid out loudWrite down which model each part uses and how the parts hand off. Unnamed hybrids fail in the seams.
  • Check you can supply what agile needsConfirm a named decision maker with real authority is available roughly every other week, before choosing the model that depends on it.
  • Let the contract follow the modelChoose the delivery approach on the merits, then write the commercial terms that fit it, in that order.

Not this

  • Choose by fashionAdopting agile because sequential sounds outdated, on a project whose requirements are set by a statute.
  • Ask for both commitmentsRequiring a fixed price against a fixed specification while also expecting to change direction freely. That is the one combination that reliably ends in a dispute.
  • Buy the ceremony onlyPaying for stand-ups, sprints and a board while skipping the automated testing that makes frequent change safe.
  • Treat agile as no planIterating without a definition of done, a pruned backlog or a release, which produces motion that is indistinguishable from progress until the money runs out.
The two questions that select a model, with real project types plottedA quadrant chart. The horizontal axis is whether a requirement can be known before building, from hypothesis to externally defined. The vertical axis is the cost of being wrong late, from recoverable to severe. Nine project types are plotted, with regulatory and medical work in the high certainty and high cost quadrant and new market products in the low certainty and recoverable quadrant. Spiral, de-risk firstV-model, verify each phaseShort incrementsIncremental slices Regulatory report Medical device Payroll rules Carrier API Payment gateway Legacy migration New market app Growth feature Internal tool Can the requirement be known before building? It is a hypothesis Externally defined Cost of being wrong late Recoverable Severe
Horizontal: can the requirement be known before you build. Vertical: what does being wrong late cost. Find the project nearest your own and read the quadrant. Positions are editorial judgment about project types, not measurements.

What each model demands from you, not from the vendor

Proposals describe what the vendor will do. The reason agile adoptions fail at the client end is that the model quietly reassigns work to the buyer, and that reassignment appears in no document anybody signs.

Sequential delivery asks a great deal of you once, at the start, and then very little. You must specify correctly, in detail, before construction begins, and that is genuinely hard. But once it is done your obligation is mostly to wait, review at agreed gates, and pay. For an organization whose subject-matter experts are busy people who can be assembled for a month and then not again, this is not a compromise. It is the only model that matches the availability you actually have.

Agile asks less of you at any single moment and much more of you in total. Someone with real authority has to be reachable, form opinions on partly built software, and decide. Not a committee that meets monthly. A person, roughly every other week, for the entire project. When that person is unavailable, the team either stalls or guesses, and a team guessing on your behalf every fortnight for six months produces something worse than a specification would have.

This is the single most useful thing a buyer can know before choosing. The question is not which model is better. It is which model matches the attention you can genuinely commit for the whole duration, and answering it honestly is worth more than any methodology preference.

Before you choose iterative delivery, confirm all six

  • A named decision maker existsOne person, not a committee, who can approve a direction change without escalating. A committee turns a two-week cycle into a six-week one.
  • That person has real availabilityA few hours every other week, for the whole project. Diary reality, not good intentions in a kickoff meeting.
  • You can act on partly built softwareReviewing something visibly incomplete and giving a useful opinion is a skill. Teams that cannot do it default to approving everything, which removes the feedback the model runs on.
  • Scope is the negotiable variableIf neither date nor budget can move, then scope must be able to. If none of the three can move, no methodology will save the project.
  • Your governance can accept a rangeIterative delivery forecasts in ranges that narrow. If procurement can only approve a single number, either fix the scope or fix that process first.
  • Engineering practices are fundedAutomated tests, a deployment pipeline, and code review. Without them, frequent change accumulates risk instead of value, and the sprints get slower.

If three or more of these are uncertain, sequential or incremental delivery will produce a better result than agile, regardless of which is more fashionable.

The arithmetic of feedback, which is the whole argument

26 Two-week increments Points a year where you can change course
4 Quarterly releases The same, an order of magnitude fewer
1 One nine-month pass A single correction point, at the end

These are not survey findings. They are division, and you can redo them for your own cadence in a few seconds, which is exactly why they are more trustworthy than an adoption statistic.

Where the work goes when you switch modelsA grouped column chart comparing relative client effort across four activities under sequential and iterative delivery. Sequential concentrates effort in specifying up front and final acceptance. Iterative concentrates it in reviewing partial work and deciding mid-project. 0 25 50 75 100Relative client effort (illustrative) 90 30Specifying up front 10 75Reviewing partialwork 15 80Deciding mid-project 70 25Acceptance at the end Sequential Iterative
Relative client effort under each model, illustrative and not measured. The bars that matter are the last two: iterative delivery moves effort out of one big specification and into a standing commitment that runs for the whole project.

Four worked examples, and what actually decided each one

The abstract version of this decision is easy to agree with and hard to apply. Here are four project shapes, drawn from the kinds of systems we build, with the reasoning that selected the model in each case.

Notice that in three of the four, the deciding factor is not the technology at all. It is who owns the requirement: a regulator, a partner's protocol, a market, or nobody yet.

Four shapes, four models, and the reason in each case

  1. A regulated clinical or pharmacy moduleV-model

    Requirements come from regulation and are not subject to preference. An auditor will ask for traceability from each requirement to the test that verifies it, so the documentation the v-model demands is documentation you must produce regardless. Iterating on a rule that is already written down buys nothing and costs the whole certification trail.

  2. A logistics platform integrating carrier APIsIncremental

    Each carrier's protocol is fixed and published, so those slices are knowable. But which carriers matter most, and how operators want the exceptions handled, is genuinely unknown. Fixed overall scope with slices delivered one carrier at a time gives an early live integration while keeping the commercial commitment intact.

  3. A consumer app entering a new marketAgile, short increments

    Almost nothing is known. Whether people will complete the signup, which feature drives retention, and what the pricing tolerance is are all hypotheses. Every week without real users is a week of building on assumptions, so short increments with genuine releases are the only model that produces information.

  4. A platform replacement with one dangerous unknownSpiral, then incremental

    The scope is largely understood, but the whole business case rests on whether twenty years of legacy data can be migrated with acceptable fidelity. Order the work by risk: prototype the migration on real data first, so the answer that could cancel the program arrives while canceling is still cheap.

The pattern worth taking away: ask who owns the requirement. If someone outside your team already owns it, iteration cannot discover it and sequential delivery is cheaper.

Five claims that survive because nobody checks them

This topic carries more received wisdom than almost any other in software, largely because it is taught alongside a moral. Each of the following is widely repeated, and each is wrong in a way that costs money.

What is claimed, and what is actually true

The claimWhat is actually the case
Agile is fasterIt delivers something usable sooner, which is not the same as finishing sooner. Total effort is often higher, because coordination and rework are how it buys early information. Speed to first value, not speed to done.
Waterfall is obsoleteIt remains standard wherever a specification is externally defined and evidence must be auditable. Aerospace, medical devices and financial reporting are not behind the times, they are correctly matched to their constraints.
Agile means no fixed dateThe date is usually the most fixed thing in the project. What flexes is scope. A team promising both a date and a complete scope while calling itself agile has quietly reverted to a specification.
You must choose oneMost serious programs run several models at once, deliberately, in different workstreams. The failure mode is not mixing them, it is mixing them without naming it.
Agile means no documentationIt means no documentation that nobody reads. Architecture decisions, interface contracts, runbooks and handover material still have to exist, because the cost of their absence is paid by whoever maintains the system for the next decade.

The fifth row is the expensive one. A team that believes it has no documentation obligation produces a system nobody can hand over, and the bill arrives after the team leaves.

The question is never whether requirements will change. It is whether you find out before or after you have built on them.

Nguyen Manh ThangChief Executive Officer, AgileTech

The consequence nobody prices: your contract has to match

This is where the choice stops being a process preference and starts costing real money. A delivery model implies a commercial shape, and the mismatches are predictable enough to name in advance.

Fixed price for a fixed scope is coherent. You specify, the vendor prices the specification and carries the estimation risk, and change requests are the mechanism for anything new. It works, and its weakness is exactly its strength: every change is a negotiation, so it punishes learning.

Time and materials against a fixed cadence is coherent. You buy a team for a period, direct it every increment, and carry the scope risk yourself in exchange for being able to change direction without renegotiating. It works, and its weakness is that it requires you to actually govern the work.

Fixed price with an agile process is the combination that produces disputes. It prices a specification while promising the freedom to change it, so the vendor must either refuse changes to protect the price, in which case you have bought waterfall at an agile price, or absorb them until the engagement becomes unprofitable and quality quietly gives way. Both parties can enter this arrangement in good faith and still end up in conflict, because the contradiction is structural rather than a matter of goodwill.

The workable middle ground is a capped increment: a fixed price per increment against a scope fixed only for that increment, with the direction reset at each boundary. You get a predictable spend rate and the vendor gets a bounded commitment. For the full detail of what a contract has to specify, and where estimates come from, see our guides to the development process and to what actually drives cost.

Which commercial shapes are coherent with which models

Fixed priceTime and materialsCapped increments
WaterfallYesPartialNo
V-modelYesPartialNo
IncrementalYesYesYes
SpiralNoYesYes
AgileNoYesYes

The single "no" is the important cell. It is not that fixed price and agile are hard to combine, it is that the combination asks the vendor to hold two incompatible commitments at once.

What changes commercially when the model changesA before and after comparison of fixed price fixed scope against capped increments, across six commercial properties including what is priced, who carries estimation risk, the cost of a mid-project change, and where disputes originate. Fixed price, fixed scope Capped increments What is priced The whole specification One increment at a time Who carries estimate risk The vendor, for everything Shared, increment byincrement Cost of a change in month four A change request and arepricing Traded against the nextincrement What you must get right early The full scope, in detail The direction andpriorities Governance you must supply Gate reviews at milestones A decision every increment Where disputes come from Whether a change was inscope Whether the rate buysenough
Not a claim that one column produces better projects. Each row states a structural property of that commercial shape, so you can check whether the shape you are being offered matches the process you were promised.

Running the decision in the right order

The order matters, because deciding the commercial terms first is the most common way to end up with the wrong process. Once a fixed price against a full specification is agreed, the project is sequential no matter what the stand-ups are called.

Split the work before choosing anything. Assess who owns each part's requirements. Check honestly what client attention you can supply. Then choose a model per workstream, and only then write the commercial terms to fit. Four steps, in that order, and reversing any two of them is how programs acquire a process that fights their contract for a year.

The four steps, and what finishing each one looks like

  1. Split the workDays

    Separate the program into workstreams by who owns the requirement: a regulator, a partner protocol, the market, or nobody yet.

    Done when A written list of workstreams, each with a named requirement owner.

  2. Assess certaintyDays

    For each workstream, ask whether the requirement is discoverable now and what it costs to be wrong late.

    Done when Each workstream marked as knowable, partly knowable, or a hypothesis.

  3. Check your own capacityOne conversation

    Confirm the decision maker and their real availability against a diary, for the whole duration.

    Done when A named person with agreed time, or an honest decision to run sequentially instead.

  4. Write the terms to matchWeeks

    Choose fixed price, time and materials, or capped increments per workstream, following the model rather than leading it.

    Done when A contract whose commercial shape and delivery model agree with each other.

Spans are indicative for a program of moderate size. The sequence is the point, not the durations: step four last is what keeps the contract from choosing the process.

Which step, when skipped, does the most damageA horizontal bar chart weighting four steps by their relative contribution to choosing a delivery model correctly. Splitting into workstreams, assessing certainty, checking client capacity and writing terms to match are all close in weight, with checking capacity highlighted as the step most often omitted. 0 10 20 30Relative contribution to a correct choice (illustrative) Splitting intoworkstreams 28 One model rarely fits all Assessing certaintyhonestly 26 Who owns the requirement Checking your owncapacity 24 The step usually skipped Writing terms to match 22 Must come last One conversation about diaries prevents the commonestfailure: a model that runs on attention nobody committed.
Illustrative weighting of how much each step contributes to getting the model right. Checking your own capacity is highlighted because it is both the cheapest step and the one most often left out entirely.

Frequently asked questions

Is waterfall really still used, or is that just legacy inertia?

It is actively chosen, and correctly, wherever the requirement is defined by someone outside your team and the evidence must be auditable. Medical devices, aerospace, and regulatory reporting all use sequential models with paired verification because a certification body needs to trace each requirement to the test that proves it. Iterating to discover a requirement that already exists in a published standard is not learning, it is a slower way of reading the standard.

What is the actual difference between SDLC and agile?

They are not alternatives, which is why the comparison confuses people. The software development life cycle is the set of activities every project performs: decide, design, build, verify, release, maintain. Agile is one way of sequencing those activities, namely repeatedly in short increments. Waterfall is another way, namely once in order. Asking whether to use SDLC or agile is like asking whether to use cooking or a recipe.

Can we run agile with a fixed price and a fixed scope?

Not coherently, and this is the most expensive misunderstanding in the field. A fixed price against a fixed specification requires the vendor to control scope in order to control cost, so either changes are refused, which means you have bought sequential delivery under an agile label, or they are absorbed until the engagement is unprofitable and quality quietly degrades. The workable version is a capped increment: fixed price per increment, scope fixed only within it, direction reset at each boundary.

Which agile framework should we ask for, scrum or kanban?

Scrum if your work arrives as a body of planned features and a regular cadence would help you make decisions. Kanban if work arrives unpredictably, as with support and operations, where a fixed sprint boundary fights reality. But the more important question is neither: ask what engineering practices the team runs. Automated tests, code review and a deployment pipeline determine whether frequent change is safe, and no amount of ceremony substitutes for them.

How do we know if our requirements are certain enough for sequential delivery?

Ask who owns each requirement. If a regulator, a published protocol, a statute or a partner's fixed interface owns it, the requirement is knowable now and sequential delivery is cheaper. If the owner is the market, or a user whose behavior you are predicting, or nobody yet, then what you have is a hypothesis written in specification format, and writing it in more detail will not make it more true.

What happens if we choose agile and cannot supply the client attention it needs?

The team either stalls waiting for decisions or makes them on your behalf. Both are worse than sequential delivery would have been, because you pay the coordination cost of iteration without receiving the information it exists to produce. If you cannot commit a named decision maker for a few hours every other week for the whole project, choose incremental delivery inside a fixed scope instead. You still get working software early, and it does not depend on availability you do not have.

Can different parts of one program use different models?

Yes, and for most serious programs that is the correct architecture rather than a compromise. A regulated core on a v-model, a platform delivered in incremental slices, and a customer-facing app on short increments is coherent, because those three parts genuinely differ in how knowable their requirements are and in what being wrong costs. The requirement is that each workstream names its model deliberately and the handoffs between them are agreed, since unnamed hybrids fail in the seams rather than in the parts.

If you want this diagnosis run on your own program before anybody quotes a price, we are a software development company in Vietnam that picks the delivery model to fit the work, and says so plainly when a specification would serve you better than a sprint.

Consult Industry Specialists

Connect with us today to discuss your software development needs and discover how our tailored outsourcing services can propel your business forward.

Start a conversation
AgileTech Vietnam team at the office

Privacy choices

We use one category of strictly necessary first-party storage, which keeps the site working and remembers this choice; it is always active. Every other category is optional and stays off until you switch it on, wherever you are in the world. Two optional categories have something behind them today: Analytics, which is Google Analytics, and External content, which is the Google map of our Hanoi office on the Contact page. Neither runs until you allow it.

Our worldwide approach. We apply one standard to everyone: nothing outside strictly necessary storage runs until you allow it. That meets the EU and UK requirement for prior consent, Vietnam's Law 91/2025/QH15 on personal data protection, the notification and consent requirements of Singapore's PDPA, and US state privacy law. You can withdraw or change your choice at any time, as easily as you gave it, from Privacy choices in the footer.

Where you are connecting from. Our network tells us the country associated with your connection, and we use it to choose which consent policy to apply. We do not use it to work out your address, we do not put it in a cookie, and we never send your IP address to the page. Today every country receives the same strict policy, so it makes no difference to what you see. If your country cannot be determined, or you are using Tor, you get the strict policy too: an unknown location always means the more protective setting, never the weaker one.

If you are in the United States. We do not sell your personal information and we do not share it for cross-context behavioral advertising, so there is nothing to opt out of. We still honor an opt-out preference signal from your browser: if your browser sends Global Privacy Control, the optional categories stay off without you having to do anything.

Full detail, including the name and lifetime of the one cookie we set, is in the Cookie Policy.